13. ![Flag for review](https://i0.wp.com/acoe.in/wp-content/plugins/watupro/img/mark-review.png?w=1880&ssl=1)
Santosh Mateti is running a 11 months project that is on track for completion within scheduled time and within budget. Nevertheless, a month before completion, he gets to know the stakeholders are dissatisfied with the deliverables and this situation is now likely to add a month's delay to the project. Which of the following processes could have prevented the situation Santosh is now facing?