This is a randomized 20-question test on Schedule Management KA of PMBoK

 5%

Question 1 of 20

1. The outcome of defining activities is
1.
2.
3.
4.

Question 1 of 20

Question 2 of 20

2. Which of the statements is true about fast tracking?
1.
2.
3.
4.

Question 2 of 20

Question 3 of 20

3. Barry is a project manager in Stoc Advisaries Inc. He is currently involved in a major upgrade to their customer facing application stock-advise. While estimating the resources, he is identifying the resources for activities at the leaf nodes of the activity breakdown structure and then aggregating the resources at summary activities and then at the project level. What estimation method is Barry likely to be using:
1.
2.
3.
4.

Question 3 of 20

Question 4 of 20

4. Project Network DiagramPlease refer to the network diagram above. In this network diagram, the free float for task D is
1.
2.
3.
4.

Question 4 of 20

Question 5 of 20

5. Tom is leading a project which is in the planning phase. And based on statistical samplings, he has determined that for a specific case, the optimistic duration estimate is 4 days, most likely estimate is 7 days and the pessimistic estimate is 9 days. What would be the 3-point estimate according to PERT distribution?
1.
2.
3.
4.

Question 5 of 20

Question 6 of 20

6. Project Network Diagramlease refer to the network diagram above. In this network diagram, the Late Start and Late Finish for task B are –
1.
2.
3.
4.

Question 6 of 20

Question 7 of 20

7. Please refer to the above network diagram. The diagram indicates that between task B and task C
1.
2.
3.
4.

Question 7 of 20

Question 8 of 20

8. A project manager has just defined the activity list for a project. What is the possible process that he should execute next?
1.
2.
3.
4.

Question 8 of 20

Question 9 of 20

9. One of the software effort estimation methodologies uses the following formula to arrive at effort:

E=ai(KLoC)(bi)(EAF)

What type of estimation methodology is this?
1.
2.
3.
4.

Question 9 of 20

Question 10 of 20

10. Project Network Diagram 
1.
2.
3.
4.

Question 10 of 20

Question 11 of 20

11. Project Network DiagramPlease refer to the network diagram above. In this network diagram, the length of the critical path is –
1.
2.
3.
4.

Question 11 of 20

Question 12 of 20

12. Project Network DiagramPlease refer to the network diagram above. In this network diagram, the critical path is –
1.
2.
3.
4.

Question 12 of 20

Question 13 of 20

13. Which of the following statement is TRUE with respect to defining activities?
1.
2.
3.
4.

Question 13 of 20

Question 14 of 20

14. Project Network DiagramPlease refer to the network diagram above. In this network diagram, the Early Start and Early Finish for task C are –
1.
2.
3.
4.

Question 14 of 20

Question 15 of 20

15. The number of days by which a task can be delayed without delaying any of its successor tasks is called
1.
2.
3.
4.

Question 15 of 20

Question 16 of 20

16. Which of the following statements is NOT true with respect to activity resource estimation process:
1.
2.
3.
4.

Question 16 of 20

Question 17 of 20

17. The outcome of sequence activities is
1.
2.
3.
4.

Question 17 of 20

Question 18 of 20

18. In a circus, there is a stunt involving swinging. There are many swingers whose legs are anchored to the swing and their hands are free for stunts. There are free swingers who perform many stunts and swing between these Anchored swingers. One unit of activity of an anchored swinger starts by holding the free swinger, continues with performing the stunts and then finishes with the anchored swinger leaving the contact of free swinger. There is a dependency in this scenario that an anchored swinger can start his stunt by holding the hand of the free swinger only after the previous anchored swinger has left the hands of the free swinger. This dependency between the activities of anchored swingers is of type
1.
2.
3.
4.

Question 18 of 20

Question 19 of 20

19. Which of the following statement is TRUE with respect to the relationship between scope and activity definition
1.
2.
3.
4.

Question 19 of 20

Question 20 of 20

20. Which of the following statements is true about Critical paths
1.
2.
3.
4.

Question 20 of 20