This is a randomized 20-question test on Schedule Management KA of PMBoK

 5%

Question 1 of 20

1. Please refer to the above network diagram. The diagram indicates that between task B and task C
1.
2.
3.
4.

Question 1 of 20

Question 2 of 20

2. Which of the following statement is TRUE with respect to the relationship between scope and activity definition
1.
2.
3.
4.

Question 2 of 20

Question 3 of 20

3. Project Network DiagramPlease refer to the network diagram above. In this network diagram, the float for task D is
1.
2.
3.
4.

Question 3 of 20

Question 4 of 20

4. Project Network Diagram 
1.
2.
3.
4.

Question 4 of 20

Question 5 of 20

5. Barry is a project manager in Stoc Advisaries Inc. He is currently involved in a major upgrade to their customer facing application stock-advise. He is working on the schedule and has just finished the RBS for the project. What process is he likely to have completed
1.
2.
3.
4.

Question 5 of 20

Question 6 of 20

6. Project Network DiagramPlease refer to the network diagram above. In this network diagram, the free float for task D is
1.
2.
3.
4.

Question 6 of 20

Question 7 of 20

7. Which of the following statements is NOT true with respect to activity resource estimation process:
1.
2.
3.
4.

Question 7 of 20

Question 8 of 20

8. Tom is leading a project which is in the planning phase. And based on statistical samplings, he has determined that for a specific case, the optimistic duration estimate is 4 days, most likely estimate is 7 days and the pessimistic estimate is 9 days. What would be the 3-point estimate according to triangular distribution?
1.
2.
3.
4.

Question 8 of 20

Question 9 of 20

9. Which of the following statements is true about Critical paths
1.
2.
3.
4.

Question 9 of 20

Question 10 of 20

10. The outcome of defining activities is
1.
2.
3.
4.

Question 10 of 20

Question 11 of 20

11. A project manager has just defined the activity list for a project. What is the possible process that he should execute next?
1.
2.
3.
4.

Question 11 of 20

Question 12 of 20

12. Which of the statements is true about fast tracking?
1.
2.
3.
4.

Question 12 of 20

Question 13 of 20

13. An estimation method uses the following formula

Estimate = (O + M + P) / 3

Where

O = Optimistic Estimate

M = Most likely estimate

P = Pessimistic estimate

This method is of the following type among estimation methodologies:
1.
2.
3.
4.

Question 13 of 20

Question 14 of 20

14. Which of the following statement is TRUE with respect to defining activities?
1.
2.
3.
4.

Question 14 of 20

Question 15 of 20

15. The outcome of sequence activities is
1.
2.
3.
4.

Question 15 of 20

Question 16 of 20

16. Barry is a project manager in Stoc Advisaries Inc. He is currently involved in a major upgrade to their customer facing application stock-advise. While estimating the resources, he is identifying the resources for activities at the leaf nodes of the activity breakdown structure and then aggregating the resources at summary activities and then at the project level. What estimation method is Barry likely to be using:
1.
2.
3.
4.

Question 16 of 20

Question 17 of 20

17. One of the software effort estimation methodologies uses the following formula to arrive at effort:

E=ai(KLoC)(bi)(EAF)

What type of estimation methodology is this?
1.
2.
3.
4.

Question 17 of 20

Question 18 of 20

18. In a circus, there is a stunt involving swinging. There are many swingers whose legs are anchored to the swing and their hands are free for stunts. There are free swingers who perform many stunts and swing between these Anchored swingers. One unit of activity of an anchored swinger starts by holding the free swinger, continues with performing the stunts and then finishes with the anchored swinger leaving the contact of free swinger. There is a dependency in this scenario that one anchored swinger can leave the contact of the free swinger only after another anchored swinger holds the free swinger. This dependency between the activities of anchored swingers is of type
1.
2.
3.
4.

Question 18 of 20

Question 19 of 20

19. Tom is leading a project which is in the planning phase. And based on statistical samplings, he has determined that for a specific case, the optimistic duration estimate is 4 days, most likely estimate is 8 days and the pessimistic estimate is 12 days. What would be the 3-point estimate according to Beta distribution?
1.
2.
3.
4.

Question 19 of 20

Question 20 of 20

20. Project Network DiagramPlease refer to the network diagram above. In this network diagram, the length of the critical path is –
1.
2.
3.
4.

Question 20 of 20