This is a randomized 20-question test on Schedule Management KA of PMBoK

 5%

Question 1 of 20

1. Barry is a project manager in Stoc Advisaries Inc. He is currently involved in a major upgrade to their customer facing application stock-advise. He has currently completed estimating resources for this project. What could he possibly do next:
1.
2.
3.
4.

Question 1 of 20

Question 2 of 20

2. One of the software effort estimation methodologies uses the following formula to arrive at effort:

E=ai(KLoC)(bi)(EAF)

What type of estimation methodology is this?
1.
2.
3.
4.

Question 2 of 20

Question 3 of 20

3. The number of days by which a task can be delayed without delaying any of its successor tasks is called
1.
2.
3.
4.

Question 3 of 20

Question 4 of 20

4. Project Network DiagramPlease refer to the network diagram above. In this network diagram, the length of the critical path is –
1.
2.
3.
4.

Question 4 of 20

Question 5 of 20

5. Which of the following statement is TRUE with respect to defining activities?
1.
2.
3.
4.

Question 5 of 20

Question 6 of 20

6. Which of the following statement is TRUE with respect to the relationship between scope and activity definition
1.
2.
3.
4.

Question 6 of 20

Question 7 of 20

7. Which of the statements is true about fast tracking?
1.
2.
3.
4.

Question 7 of 20

Question 8 of 20

8. Project Network Diagram 
1.
2.
3.
4.

Question 8 of 20

Question 9 of 20

9. The outcome of sequence activities is
1.
2.
3.
4.

Question 9 of 20

Question 10 of 20

10. Project Network DiagramPlease refer to the network diagram above. In this network diagram, the free float for task D is
1.
2.
3.
4.

Question 10 of 20

Question 11 of 20

11. A project manager has just defined the activity list for a project. What is the possible process that he should execute next?
1.
2.
3.
4.

Question 11 of 20

Question 12 of 20

12. In a circus, there is a stunt involving swinging. There are many swingers whose legs are anchored to the swing and their hands are free for stunts. There are free swingers who perform many stunts and swing between these Anchored swingers. One unit of activity of an anchored swinger starts by holding the free swinger, continues with performing the stunts and then finishes with the anchored swinger leaving the contact of free swinger. There is a dependency in this scenario that one anchored swinger can leave the contact of the free swinger only after another anchored swinger holds the free swinger. This dependency between the activities of anchored swingers is of type
1.
2.
3.
4.

Question 12 of 20

Question 13 of 20

13. Project Network DiagramPlease refer to the network diagram above. In this network diagram, the Early Start and Early Finish for task C are –
1.
2.
3.
4.

Question 13 of 20

Question 14 of 20

14. Barry is a project manager in Stoc Advisaries Inc. He is currently involved in a major upgrade to their customer facing application stock-advise. While estimating the resources, he is identifying the resources for activities at the leaf nodes of the activity breakdown structure and then aggregating the resources at summary activities and then at the project level. What estimation method is Barry likely to be using:
1.
2.
3.
4.

Question 14 of 20

Question 15 of 20

15. Project Network DiagramPlease refer to the network diagram above. In this network diagram, the critical path is –
1.
2.
3.
4.

Question 15 of 20

Question 16 of 20

16. Project Network DiagramPlease refer to the network diagram above. In this network diagram, the float for task D is
1.
2.
3.
4.

Question 16 of 20

Question 17 of 20

17. Tom is leading a project which is in the planning phase. And based on statistical samplings, he has determined that for a specific case, the optimistic duration estimate is 4 days, most likely estimate is 8 days and the pessimistic estimate is 12 days. What would be the 3-point estimate according to Beta distribution?
1.
2.
3.
4.

Question 17 of 20

Question 18 of 20

18. Project Network Diagramlease refer to the network diagram above. In this network diagram, the Late Start and Late Finish for task B are –
1.
2.
3.
4.

Question 18 of 20

Question 19 of 20

19. Tom is leading a project which is in the planning phase. And based on statistical samplings, he has determined that for a specific case, the optimistic duration estimate is 4 days, most likely estimate is 7 days and the pessimistic estimate is 9 days. What would be the 3-point estimate according to PERT distribution?
1.
2.
3.
4.

Question 19 of 20

Question 20 of 20

20. The outcome of defining activities is
1.
2.
3.
4.

Question 20 of 20