This is a randomized 20-question test on Schedule Management KA of PMBoK

 5%

Question 1 of 20

1. Barry is a project manager in Stoc Advisaries Inc. He is currently involved in a major upgrade to their customer facing application stock-advise. He is working on the schedule and has just finished the RBS for the project. What process is he likely to have completed
1.
2.
3.
4.

Question 1 of 20

Question 2 of 20

2. Project Network DiagramPlease refer to the network diagram above. In this network diagram, the critical path is –
1.
2.
3.
4.

Question 2 of 20

Question 3 of 20

3. Tom is leading a project which is in the planning phase. And based on statistical samplings, he has determined that for a specific case, the optimistic duration estimate is 4 days, most likely estimate is 7 days and the pessimistic estimate is 9 days. What would be the 3-point estimate according to PERT distribution?
1.
2.
3.
4.

Question 3 of 20

Question 4 of 20

4. Tom is leading a project which is in the planning phase. And based on statistical samplings, he has determined that for a specific case, the optimistic duration estimate is 4 days, most likely estimate is 8 days and the pessimistic estimate is 12 days. What would be the 3-point estimate according to Beta distribution?
1.
2.
3.
4.

Question 4 of 20

Question 5 of 20

5. A project manager has just defined the activity list for a project. What is the possible process that he should execute next?
1.
2.
3.
4.

Question 5 of 20

Question 6 of 20

6. Please refer to the above network diagram. The diagram indicates that between task B and task C
1.
2.
3.
4.

Question 6 of 20

Question 7 of 20

7. An estimation method uses the following formula

Estimate = (O + M + P) / 3

Where

O = Optimistic Estimate

M = Most likely estimate

P = Pessimistic estimate

This method is of the following type among estimation methodologies:
1.
2.
3.
4.

Question 7 of 20

Question 8 of 20

8. Barry is a project manager in Stoc Advisaries Inc. He is currently involved in a major upgrade to their customer facing application stock-advise. While estimating the resources, he is identifying the resources for activities at the leaf nodes of the activity breakdown structure and then aggregating the resources at summary activities and then at the project level. What estimation method is Barry likely to be using:
1.
2.
3.
4.

Question 8 of 20

Question 9 of 20

9. Project Network DiagramPlease refer to the network diagram above. In this network diagram, the free float for task D is
1.
2.
3.
4.

Question 9 of 20

Question 10 of 20

10. The outcome of sequence activities is
1.
2.
3.
4.

Question 10 of 20

Question 11 of 20

11. Project Network DiagramPlease refer to the network diagram above. In this network diagram, the Early Start and Early Finish for task C are –
1.
2.
3.
4.

Question 11 of 20

Question 12 of 20

12. Project Network DiagramPlease refer to the network diagram above. In this network diagram, the length of the critical path is –
1.
2.
3.
4.

Question 12 of 20

Question 13 of 20

13. Which of the statements is true about fast tracking?
1.
2.
3.
4.

Question 13 of 20

Question 14 of 20

14. Which of the following statement is TRUE with respect to defining activities?
1.
2.
3.
4.

Question 14 of 20

Question 15 of 20

15. Project Network DiagramPlease refer to the network diagram above. In this network diagram, the float for task D is
1.
2.
3.
4.

Question 15 of 20

Question 16 of 20

16. The PERT estimate of duration for a task is 12 days which has an optimistic estimate of 6 days and a most likely estimate of 10 days. What is the pessimistic estimate?
1.
2.
3.
4.

Question 16 of 20

Question 17 of 20

17. Tom is leading a project which is in the planning phase. And based on statistical samplings, he has determined that for a specific case, the optimistic duration estimate is 4 days, most likely estimate is 7 days and the pessimistic estimate is 9 days. What would be the 3-point estimate according to triangular distribution?
1.
2.
3.
4.

Question 17 of 20

Question 18 of 20

18. Which of the following statement is TRUE with respect to the relationship between scope and activity definition
1.
2.
3.
4.

Question 18 of 20

Question 19 of 20

19. Project Network Diagramlease refer to the network diagram above. In this network diagram, the Late Start and Late Finish for task B are –
1.
2.
3.
4.

Question 19 of 20

Question 20 of 20

20. The number of days by which a task can be delayed without delaying any of its successor tasks is called
1.
2.
3.
4.

Question 20 of 20