4.1 Develop project charter

InputsTools and TechniquesOutputs
Project statement of workExpert judgmentProject charter
Business caseFacilitation techniques
Agreements
Enterprise environmental factors
Organizational process assets

Inputs

Project Statement of Work (SOW

Is a narrative description of products, services or results to be developed by a project. SOW covers the business need, product scope description, strategic plan.

Business Case

A document that determines whether or not the project is worth the required investment

Agreements

Agreements are used to define initial intention of the project. They can be Memorandum of Understanding (MOU), Service Level Agreements (SLAs), Letters of Intentions (LOIs) etc.

Enterprise Environmental Factors

Organizational Process Assets

Please refer to the common ITTO section.

Tools and Techniques

Facilitation techniques

Please refer to the common ITTO section

Output

Project Charter

Is the document issued by the project initiator (sponsor) that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.

Back to PMBoK table

4.2 Develop project management plan

 

InputsTools and techniquesOutputs
Project charterExpert judgmentProject management plan
Outputs from other processesFacilitation techniques
Enterprise environmental factors
Organizational process assets

Input

Project charter

Outputs from other processes

Outputs from other process, especially in the planning process group such as cost baselines, schedule baselines etc.

EEF

OPA

Please refer to the common ITTO section.

Tools and Techniques

Expert Judgment

Facilitation Techniques

Please refer to the common ITTO section.

Output

Project Management Plan

It is the document that includes all the subsidiary plans such as scope management plan, schedule management plan, cost management plan, scope baseline etc.

Back to PMBoK table

4.3 Direct and Manage Project Work

 

InputsTools and techniquesOutputs
Project management planExpert judgmentDeliverables
Approved change requestsProject management information systemWork performance data
Enterprise environmental factorsMeetingsChange requests
Organizational process assetsProject management plan updates
Project document updates

 

Input

Project Management Plan

Approved Change Requests

These are change requests approved by the change control board (CCB) for implementation which may be a corrective action, a preventive action or a defect repair.

EEF

OPA

Please refer to the common ITTO section.

Tools and Techniques

Expert Judgment

Meetings

Please refer to the common ITTO section.

Project Management Information System

Information flow systems such as an intranet based status tracking took, a scheduling tools and so on.

Output

Deliverables

Any unique and verifiable product, result or capacity to perform service that is required to complete a process, project or phase. Typically engineering deliverables that make the end product or service.

Work performance data

Lowest level of detail in the project. Raw observations resulting from task executions. Examples are defects, issues, task status. It is an output of the process 4.3 Direct and Manage Project Work.

Change request

A formal proposal to modify any document deliverable or baseline which will be evaluated and disposed by the change control board (CCB).

Project Management Plan Updates – self explanatory.

Project Document Updates 

Project documents other than project management plan are requirements document, risk register, change log, stakeholder register and so on.

Back to PMBoK table

4.4 Manage project knowledge

Input

Project Management Plan

Project Documents

Deliverables

EEF

OPA

Please refer to the common ITTO section

Tools and Techniques

Expert Judgment

Knowledge Management

Information Management

Interpersonal and Team skills

Please refer to the common ITTO section

Outputs

Lessons learned register

Project Management Plan Updates 

OPA Updates

Back to PMBoK table

4.5 Monitor and Control Project Work

InputsTools and techniquesOutputs
Project management planExpert judgmentChange requests
Validated changesProject management information systemWork performance reports
Enterprise environmental factorsMeetingsProject management plan updates
Organizational process assetsAnalytical techniquesProject document updates
Schedule forecasts
Cost forecasts
Work performance information

 

Input

Project Management Plan

Schedule forecasts (to be described in Schedule Management KA)

Cost forecasts (to be described in Cost Management KA)

Validated Changes

Implemented change requests that have gone through a validation such as a review or testing. This is further used to close the change request.

Work performance information

Information derived by analyzing the work performance data. For example, the impact of a task delay (Work performance data) on the overall project duration, the schedule forecast (Work performance information) is derived by analyzing work performance data. This is an output of many controlling processes such as ‘control cost’, ‘control schedule’, ‘control quality’ etc.

EEF

OPA

Please refer to the common ITTO section

Tools and Techniques

Expert Judgment

Analytical Techniques

Project Management Information System

Meetings

Please refer to the common ITTO section

Outputs

Change requests

Work performance report

A project status report that is sent to stakeholders.

Project Management Plan Updates – Self explanatory

Project Document Updates – Self explanatory

Back to PMBoK table

 

4.6 Perform Integrated Change Control

 

InputsTools and techniquesOutputs
Project management planExpert judgmentApproved change requests
Work performance reportsMeetingsChange log
Enterprise environmental factorsChange control toolsProject management plan updates
Organizational process assetsProject document updates
Change requests

 

Input

Project Management Plan

Work Performance Reports – Details the change requests newly raised and change requests that are validated and can be closed.

Change Requests

EEF

OPA

Tools and Techniques

Expert Judgment

Meetings

Change Control Tools

Manual tools or software tools used to raise change requests, review change requests, approve and dispose the change requests and track their status throughout.

Output

Approved Change requests

Change log

Change requests are reviewed in this process and are either approved or rejected. Accordingly change requests that are approved or change log updated with the information of rejection of a change request are among the outputs of this process

Project Management Plan Updates – Self explanatory

Project Document Updates – Self explanatory

Back to PMBoK table

4.7 Close Project Or Phase

 

InputsTools and techniquesOutputs
Project management planExpert judgmentFinal product, service or result transition
Accepted deliverablesMeetingsOrganizational process assets updates
Organizational process assetsAnalytical techniquesProject document updates

 

Input

Project Management Plan

Accepted Deliverables

The final deliverables that comprise the product, service or result that the customer has reviewed and deemed accepted.

OPA

Tools and Techniques

Expert Judgment

Meetings

Analytical Techniques

Please refer to the common ITTO section

Outputs

Final product service or result transition

The outcome of the project has to be transitioned to the next stage such as operations and this transition is the output of this process.

OPA updates